| Week |
Process |
Process |
| Week 1 |
Water Utility begins replacing lead connections |
First holes in your street |
| Week 2 |
Xcel begins replacing gas mains |
Sewer repairs done if needed |
| Week 3 |
Letters, fliers from City notify residents of construction a week before it starts |
|
| Week 4 |
Letters, fliers from City notify residents of construction a week before it starts |
|
| Week 5 |
Contractor begins to remove street |
Your access is limited |
| Week 6 |
Storm sewer inlets built |
|
| Week 7 |
Gravel base is placed |
Access improved |
| Week 8 |
Concrete curbs built |
Street light conduit installed in boulevard |
| Week 9 |
Concrete driveways are poured |
Driveways unusable for two weeks |
| Week 10 |
Concrete driveways are poured |
|
| Week 11 |
First layer of asphalt placed |
Access to home near normal |
| Week 12 |
Boulevards sodded |
|
| Week 13 |
Final layer of asphalt placed |
|
| Week 14 |
Street lights installed and turned on |
Trees installed when weather allows |