CONSTRUCTION UPDATE AND PROJECT ARCHIVE

To view an archive of Construction Updates, click here.


Week of September 26th Construction Update

Beechwood, Rome, and Saunders Avenues:  Sodding completed west of Davern Street.

Hillcrest Avenue:  Pavement removal started and water main completed.

Howell Street:  Pavement removal started.       

Week of October 3rd Planned Construction

Hillcrest Avenue:  Continue pavement removal, begin work on re-tapping water
services, sanitary sewer services, and storm sewer work.

Howell Street:  Continue pavement removal, begin work on sanitary sewer services,
and the storm sewers.      


Project Inspector: Ryan Lowry                        

Cell: 651-775-6674
Office: 651-266-6147