The original cast iron water main within the project area was installed in 1925 and has experienced repeated main breaks over the years. To continue to ensure the reliability of our system, SPRWS regularly replaces aging infrastructure that may be susceptible to breaking with newer, more dependable infrastructure.
SPRWS will be hiring a contractor to replace the existing 6" cast iron water main with 8" HDPE pipe using a method called pipe bursting.
Project Scope:
- Replace 1,200 ft of 6" water main
- Replace valves and hydrants
- Restore street pavement as needed
Project Updates
Temporary water main setup is
Temporary water main setup is in progress. Water main replacement to follow.
- Log in to post comments
Project Updates
Water main replacement is in
Water main replacement is in progress. Work to continue in the coming weeks.
- Log in to post comments
Project Updates
Water main work is nearing
Water main work is nearing completion. Restoration work to follow.
- Log in to post comments