Wabasha Street Reconstruction

Wabasha Street Project Map Snapshot

Street reconstruction includes:

  • Bituminous pavement
  • Boulevard trees
  • Concrete curb and gutter
  • Concrete outwalks and driveway aprons
  • Lantern-style street lighting
  • Public art
  • Sewer and water main repairs as needed
  • Sodded boulevards
  • Storm sewer catch basins

Traffic Impact

  • Full road closure

Project Updates

Friday, July 21, 2017

 

Work completed this week

  • Water main work continued.
  • The Wabasha Street Bridge was closed for two days for storm sewer work and to place the road base in the Water Street/Fillmore Avenue intersection.
  • Utilities were relocating their facilities on the west side of Wabasha Street.

Planned construction for next week

  • Water main work should be completed.
  • Additional storm sewer work will be done mid-block on Wabasha Street.
  • Additional road base work will be on done on Wabasha Street.
  • Utilities should be done with their work on the west side of Wabasha Street.

Road construction can be disruptive — we appreciate your cooperation and patience.  For your safety and that of the crews, please drive safely through work zones.

Thank you!