Seminole Main Rep

Project Engineer: Kaitlin Swanson 651-266-6289

The original cast iron water main within the project area was installed in 1948 and has experienced repeated main breaks over the years. To continue to ensure the reliability of our system, SPRWS regularly replaces aging infrastructure that may be susceptible to breaking with newer, more dependable infrastructure.

SPRWS will be hiring a contractor to replace the existing 6" cast iron water main with 8" HDPE pipe using a method called pipe bursting.

Project Scope:

  • Replace 600 ft of 6" water main
  • Replace valves and hydrants
  • Restore street pavement as needed

Project Updates

Contractor will be performing pre-work in the project area to prepare for project start later in the construction season. Specific start dates to be determined.

Project Updates

Tentative project start date of May 31st.

Project Updates

Temporary water supply setup to begin the week of June 14th
Excavation and water main replacement to begin the week of June 21st.