Saint Paul Streets Process
Each contractor schedules work differently, but paving and utility work take an average of 14-weeks. Bad weather and/or unforeseen problems will add to that timeframe. Reconstruction can start as early as April or as late as September.
- Water utility begins replacing lead connections
- Xcel Energy begins replacing gas mains
- Letter/flyers from the City of Saint Paul update residents of construction start 1-week prior
- Contractor begins street removal and begins watermain construction
- Storm sewer inlets are built
- Gravel base is placed
- Concrete curbs are placed
- Concrete driveways are poured
- Base layer of asphalt is placed
- Boulevards are prepped and sodded
- Final layer of asphalt is placed
- Street lights are installed and activated
- Trees are planted as weather permits
Map of Saint Paul Streets Anticipated Reconstruction Projects