Project Details

Description
The project is constructing 5 "Nodes" along the Grand Round at locations identified within the Grand Round Implementation Plan. Each node will include:

  • Informational Kiosk
  • Seatwall
  • bike racks
  • fix-it stations
  • waste receptacle
  • Grand Round branding
  • Wayfinding signage

Each node will share a similar design elements to those previously constructed along Wheelock Parkway and Como Avenue. 

Location
This project will take place at various locations along the Grand Round. These locations include:

  1. 1356 Lexington Parkway North, Saint Paul, MN 55103

  2. Wheelock Parkway and East Como Boulevard, Saint Paul, MN 55103

  3. 1264 Burns Avenue, Saint Paul, MN 55106

  4. 1244 Johnson Parkway, Saint Paul, MN 55106

  5. Pelham Boulevard and Mississippi River Boulevard, Saint Paul, MN 55104

Because of the small size of each of these project locations, we expect minimal disruptions to the adjacent pathways. The contractor will provide an alternative route for pedestrian and bike traffic safely around each site and secure the locations when they are not present.  

Timeline
June 2022 to September 2022

Project Updates

May 24, 2022 - Construction Activities to begin starting Tuesday May 31st at 1264 Burns Avenue and 1244 Johnson Parkway. 

Last Edited: May 24, 2022