A replacement design process began with the the formation of a design task force made up of community members, city staff and external aquatic consultants.
(All design task force meetings were open to the public for observation, but concerns/comments from non-task force members were voiced through the appropriate task force representative)
Project Manager:
Don Ganje, Landscape Architect
Ph: (651) 266-6425
Design Development
Development of the construction plans and specifications for the pool, bath house, concessions building, and parking lots is currently under way.
Bidding of the project is anticipated for early August.
Construction Schedule
September 2010 - Sitework
October 2010 - Beach House foundations and walls
December 2010 - February 2011 - Mechanical rooms
March 2011 - Pool Equipment
April 2011 - Rockwork
May 2011 - Lazy River excavation and forms/rockwork
July 2011 - Pool decks
September 2011 - Pool Start-up and winterization
May 2012 - Grand Opening