Expo Area Safe Routes to School Sidewalk Infill Project

PWSDC Expo Map September 2018.PNG

Project Updates

Thursday, November 1, 2018

This week

  • Restoration work including the installation of trees, edging, and placement of topsoil and sod along new sidewalk has been completed.
  • Final clean-up and sweeping is expected to be complete by end of day Friday, October 2.

Sod maintenance

  • New sod has already been fertilized.  We ask that you not apply additional fertilizer until spring.  Earlier applications will destroy the sod.
  • The contractor will water the sod for 30-days after which time it will become the sole responsibility of the property owner/resident to maintain.
  • Please keep your mower at its highest setting to avoid damaging the sod.

Project punch-list items

  • Punch-list items are being developed and will be provided to the contractor.  Items will be scheduled intermittently and/or may be completed in 2019.