The original cast iron water main within the project area was installed in 1973.

It has suffered repeated breaks over the years and has exceeded its useful life. 

SPRWS crews along with Quam Construction Co. will replace the existing 6” cast iron water main with 8” HDPE pipe via a trenchless method called pipe bursting.

Project Scope:

  • Replace 1,300 ft. – 6” water main
  • Replace valves and hydrants
  • Restore street pavement as needed