Como Avenue Paving Phase II

PWSDC Como 2018 Project Map Without 2.jpg

Project Updates

Thursday, June 14, 2018

 

‚ÄčThis week

  • Watermain installation at Brompton Street and Hendon Avenue.
  • Storm sewer work.
  • Began sanitary sewer manhole rebuilds.

Next week

  • Hook-up water services to houses and buildings.

Traffic

  • Regular traffic will be re-routed using Valentine Avenue and Eustis Street.
  • Eastbound traffic to turn south on Eustis Street to Valentine Avenue.
  • Westbound traffic to turn west on Valentine Avenue to Eustis Street.
  • The intersection of Como/Brompton/Hendon will close for 20-days starting Thursday, June 7.  The detour will remain the same.

Note

  • Phase I of the project is on track to be completed the first week in July.