Total Cost
$84,464.00
2018 Actual Frontage
722.00
Estimated Rate per Foot (50% of Cost)
$58.49
Remove the top 2-inches of the roadway and replace with a new layer of bituminous pavement
Total Cost
$84,464.00
2018 Actual Frontage
722.00
Estimated Rate per Foot (50% of Cost)
$58.49