
Aerial image of map (PDF)
SPRWS is partnering with Ramsey County to complete the reservoir demolition as part of the County’s Charles M. Schulz Highland Arena and parking lot improvements project.
Tentative Project Status and Timeline
- Design and estimating services – September - November 2020
- Planning, permitting, procurement – December 2020 - March 2021
- Demolition – April 2021 - October 2021
Project Contacts
Highland Reservoir No.1 Demolition:
Kaitlin Swanson
Project Manager
651-706-1614
Charles M. Schulz Highland Arena and Parking Lot Improvements:
Ryan Ries
Project Manager
651-266-0310
Project Updates
May 21st Update
Starting the week of May 24th, work will begin to excavate and remove material from the top of the reservoir. Additional work will be occurring to abandon water main on the west side of the reservoir.
- Log in to post comments
Project Updates
June 2nd Update
Excavation by the contractor has begun at the reservoir. SPRWS work to abandon water main should complete by the end of the week.
- Log in to post comments
Project Updates
June 22nd Update
Demolition, export, and earthwork at former reservoir area is ongoing and will
continue into August.
Utility work in the south parking lot area will start June 28th, likely starting at the south end.
- Log in to post comments
Project Updates
September 9th Update
Grading and seeding of the reservoir site is in progress.
- Log in to post comments
Project Updates
October 6th Update
Demolition and excavation work complete. Minor site grading and cleanup in progress.
- Log in to post comments