Mississippi River Boulevard Main Replacement (Randolph to Jefferson)

MRD Rand Map

If you live in this area and are to be placed on temporary water service during construction, we need your help.
Your outside water faucet and inside water meter shut off valves need to be in working order for us to provide you with temporary water.

Find Out More

The original cast iron water main within the project area was installed in the early 1920s and has experienced repeated main breaks over the years. To continue to ensure the reliability of our system, SPRWS regularly replaces aging infrastructure that may be susceptible to breaking with newer, more dependable infrastructure.

SPRWS will be hiring a contractor to replace the existing 6" cast iron water main with 6" HDPE pipe using a method called pipe bursting.

Project Scope:

  • Replace 1,300 ft of 6" water main
  • Replace valves and hydrants
  • Restore street pavement and turf as needed

Project Updates

Wednesday, July 15, 2020

Project is complete.

Friday, July 10, 2020

Water main replacement is complete. Restoration is in progress.