Project Details

Description
The original cast iron water main in the project area was installed between 1924 and 1962 and has experienced repeated main breaks over the years. To continue to ensure the reliability of our system, SPRWS will be replacing the existing 6" cast iron water main with 6" and 8" HDPE using a method called pipe bursting. The scope of the project is as follows:

  • Replace approximately 2,100 feet of 6" cast iron water main on Bernard with 8" HDPE
  • Replace approximately 1,300 feet of 6" cast iron water main on Sperl with 6" HDPE
  • Replace necessary valves and hydrants in the project area
  • Repair and restore any areas disturbed by project activities via a full mill and overlay on both streets

Location
Bernard Street from Oakdale Avenue to Felix Street
Sperl Street from Haskell Street to Arion Streets

Timeline
Project is tentatively scheduled to begin in late April of 2023 and continue through early July.

Contact
Project Engineer: Matt Dalrymple 651-266-6887