Cleveland/Prior/St. Clair Pedestrian Improvements

Project Update

Questions?  Contact Project Inspector Bill Vos at 651-755-1246

July 18, 2019

This week

  • Sawed pavement on Prior Avenue

Next week

  • Remove pavement, curb, and walk on the east side of Prior Avenue, beginning at Summit Avenue moving north.
  • Replace curb on the east side of Prior Avenue.

 


As part of the city’s mill and overlay program, pedestrian ramps will be brought up to ADA-compliance with certain pedestrian improvements such as bump-outs and sidewalk infill also occurring.

Concrete work prior to the mill and overlay will begin on the following streets:

  • Cleveland Avenue from Yorkshire Avenue to Mississippi River Boulevard
  • Prior Avenue from Roblyn Avenue to Summit Avenue
  • St. Clair Avenue from Fairview Avenue to Snelling Avenue