Grand Avenue Pedestrian Safety Improvements

PWSDC Grand Avenue Map for Website.PNG

Project Updates

Thursday, October 25, 2018

This week

  • Work, including restoration of topsoil and sod, is complete.
  • New signage has been installed.  
  • Pavement crosswalk markings are being completed.  Installations are impacted by air temperature and the cold temperatures have delayed installations at some intersections.

Traffic

  • All intersections and sidewalk areas are fully open and traffic control has been removed.
  • Temporary impacts during work on punch-list items.

Note

  • A list of punch-list items is being developed.  This list will be provided to the contractor and identified items will be addressed intermittently.  
  • Additional warranty work may be performed in 2019.