Hatch-Park Paving Schedule Map V2
Due to a scheduling conflict with the contractor, the paving schedule has been slightly modified. See attached Hatch-Park Paving Schedule Map (Updated 10/7/2025). Parking restrictions will be enforced on these days for selected streets. Mill and paving operation starting this week.
This Week
- Milling on various streets
- Paving to start on Thursday, October 9th
- Hydroseed around new sidewalk/concrete areas; contractor will be responsible for watering for the first 30 days
- Continued with tree removal
Anticipated Work Next Week
- Paving continues on various streets
- Complete hydroseeding
- Installing new signage
Traffic Impacts
- Residents will have access to the neighborhood and driveways
- Sidewalk access will be maintained on one side of the street (impacts will be for about a week following removal of sidewalks and ped ramps)
- Temporary No Parking will be installed at various locations; no parking from 7AM - 7PM
- Little to no impact to recycle/trash collection
Safety
- Please do not move traffic control signs or barrels as they are there for everyone's safety and to keep cars from driving through the construction site
- Use caution when navigating the area while curbs and ramps are installed
- Please slow down while driving through the project area
- Cars will be ticketed and towed if parked in a no parking area
Project Contacts
All construction to be completed in 2025, weather permitting