Rankin Main Rep

Project Engineer: Tom Jauquet 651-266-6271

There is no existing water main on Rankin Street between Youngman and Steward. In order to create better flow conditions in the area, SPRWS will be installing a 6" ductile iron water main. A contractor will be hired to provide excavation and restoration of the roadway for the project.

Project Scope:

  • SPRWS to install approximately 350 feet of new 6" main
  • Contractor to excavate and restore street pavement, curb, and sidewalk as needed

Project Updates

Excavation to begin October 7th with main replacement work to begin the week of October 11th.

Project Updates

Main replacement work is complete. Restoration is in progress.