Description
Neighborhood street and pedestrian improvements within the area of East Como Boulevard, Grotto Street, Maryland Avenue, and Arlington Avenue are planned for 2025 and 2026. The project will improve street pavement, curb and gutter, street lighting, sidewalks, underground utilities including water mains and storm sewers as well as improve pedestrian safety by filling in missing sidewalk gaps.

Location
Phase 1

  • Como Boulevard East between Arlington Avenue and Lakeview Avenue
  • Parkview Avenue between Como Boulevard and Victoria Street
  • Ivy Avenue between Como Boulevard and Grotto Street
  • Orange Avenue between Osage Street and Folsom Street
  • Osage Street between Ivy Avenue and Victoria Street
  • Avon Street between Lakeview Avenue and Wheelock Parkway
  • Folsom Street between Ivy Avenue and Wheelock Parkway

Timeline
2025 - Phase 1
2026 - Phase 2

Tags

    August 4-8 East Como Boulevard Closures

    • August 4 to August 8, East Como Boulevard from Parkview to Arlington will be closed to traffic from 7 a.m. to 7 p.m.
    • August 4 to August 8, East Como Boulevard from Lakeview to Parkview will be closed to traffic from 7 a.m. to 7 p.m.

    Construction started on July 14, 2025, and is anticipated to continue through November 2025. There are many street segments included in this project. Specific work locations and schedule are dependent on weather and contractor’s capacity. Work may not always be happening on your block.

    The contractor intends to begin work on East Como Boulevard and Parkview Avenue, and then move southeastward. 

    General order of street construction (each block or roadway section will likely be on a different schedule):

    • Removal of existing roadway
    • Underground utility work
    • Construction of concrete curb and gutter
    • Construction of roadway
    • Installation of new sidewalk and pedestrian ramps
    • Final layer of roadway asphalt
    • Boulevard restoration
    • Tree plantings, often happen the following year

    For more details on construction, see the  Construction Notification letter.

    Project Updates

    All construction activities and traffic impacts are weather and schedule permitting and subject to change.

    Saint Paul Regional Water Services: Lead Service Line Replacement

    Saint Paul Regional Water Services (SPRWS) has completed replacement of lead water service lines in the Wheelock-Grotto Phase 1 area.

    SPRWS is replacing lead water service lines in the Wheelock-Grotto Phase 1 area at no cost to property owners.

    SPRWS is contacting residents directly to coordinate lead service line replacement. In order to complete this work, staff need access to the inside of the property.

    This work is being done in advance of the street reconstruction project. Holes in the street, sidewalk, and/or boulevard will not be fully repaired at this time. Gravel and other temporary materials may be used to make the area safe and accessible. The final restoration of the street, sidewalk, and/or boulevard will be done with the street reconstruction project.

    For questions about lead service line replacement, contact SPRWS Brent Marsolek at 651-266-6810 or brent.marsolek@ci.stpaul.mn.us

    More information about lead service line replacement is available at on the Lead Free webpage.

    Sewer Work - Nearby

    Starting on Monday, June 30, Saint Paul Sewer Utility is doing some work on storm drains on Victoria. They will be doing some storm sewer repairs, and will need to remove some pavement in the work area. The pavement will be repaved shortly after the work is completed. This work is NOT part of the Wheelock-Grotto Street Reconstruction Phase 1 project.

    Private Property Sewer Work

    Property owners are responsible for their private sanitary sewer lines that are under the roadway and connect to the city’s main sewer line. Because the street is being reconstructed, it is a good time to undertake needed or preventative work/repairs on your private sanitary sewer line. The project encourages everyone to have their sanitary sewer connection inspected to verify its condition. For questions, contact the Sewer Utility service desk at 651-266-6234 or PW-SewerCounter@ci.stpaul.mn.us.

    Sidewalks

    The city is committed to making Saint Paul a pedestrian friendly, walkable community for everyone. In February 2017, the Saint Paul City Council adopted a policy of installing sidewalks where none exist as an integral part of all reconstruction projects. 

    The project will incorporate sidewalk recommendations from the 2023 Como Park High School and Como Park Elementary Safe Routes to School Plan within the project limits. The plan was developed by Saint Paul Public Schools staff and students along with the City of Saint Paul. It includes recommendations for street improvements near the two schools with the goal of increasing the number of students and families who walk and bike to school. The plan recommends sidewalks where there are none.

    Update 2/19/25: Revised Sidewalk Plan

    Engineering staff analyzed the survey data of existing topographic conditions and have made revised recommendations for placement of new sidewalk within the project area. The revised map shows the recommended placement of sidewalks. The revised sidewalk plan still follows existing city policy. 

    Public Works analyzed the existing terrain. Sidewalks are not recommended in areas that would require the installation of a retaining wall. Placing the sidewalk at the bottom of the slopes would reduce boulevard width, impact trees, and reduce available snow storage space. The revised sidewalk plan provides adequate space for snow storage, future tree plantings, and concurrent sidewalks on every block while preserving as much existing tree canopy as possible. 

    The standard placement for sidewalk installation is at the private property line. The city will work around existing trees and infrastructure where possible.

    Detailed Sidewalk Layout Map

    Use the revised  detailed sidewalk layout map to view the proposed layout of new sidewalks and location of existing sidewalks in the Wheelock-Grotto Phase 1 area. 

    Detailed Map Sections

    Please note that this map is for informational purposes and may not exactly reflect the existing infrastructure or final construction.

    Understanding and using the sidewalk layout map:

    • Zoom in to the specific street or property address (property lines are in green and buildings are in turquoise with addresses on them)
    • Map key
      • Green lines = property lines and recorded right of way (green lines along the street and alley)
      • Yellow = existing sidewalk
      • Dark orange = existing fence or wall
      • Green bubbles with number = existing tree and number is the size of the tree's trunk in inches
      • Blue lines = proposed curb for reconstructed street
      • Light orange with dots = proposed sidewalk
      • Olive green with number = width of the public right of way and proposed street in feet
      • Black boxes with a letter = driveways
        • A = asphalt driveway
        • B = brick driveway
        • C = concrete driveway
        • G = gravel driveway
    • Legend for the sidewalk map

    Virtual Meeting March 11

    2024 Video Presentations

    Please watch the Wheelock-Grotto Phase 1 video presentation (September 2024) to learn more about the project. You can also view the PowerPoint slides used in the video.

    Please watch the Wheelock-Grotto Phase 1 sidewalks video presentation (October 2024) to learn more about the layout of new sidewalks in the project area. You can also view the PowerPoint slides used in the sidewalks video. Please note that some of this information has changed with the Revised Sidewalk Plan shared on February 19, 2025.

    See the sidewalk section below to view the detailed sidewalk layout map used in the sidewalk presentation. Use this sidewalk map to view the layout of the sidewalk along specific streets or properties.