Construction Schedule
- Week of June 1 - construction activities anticipated to begin, including placement of construction signs and temporary water main
- Starting June 15 - removals are expected to start
There are many street segments included in this project. Specific work locations and schedules are dependent on weather and the contractor’s capacity. Work may not always be happening on your block.
The contractor intends to begin work on East Como Boulevard and Lakeview Avenue early to mid-June, 2026 and then move southeastward.
Map showing the order of anticipated construction by area
General order of street construction (each block or roadway section will likely be on a different schedule):
- Construction set up, including signage and temporary water mains
- Removal of existing roadway
- Underground utility work
- Construction of concrete curb and gutter
- Construction of roadway
- Installation of new sidewalk and pedestrian ramps
- Final layer of roadway asphalt
- Boulevard restoration
- Tree plantings (often happen the following year)