Parque Castillo

Parque Castillo Project Overview

Project Description

This project will replace the existing Parque Castillo play area to meet current safety standards. Additionally, site improvements such as landscaping, walkways, and other site features will be included to create a vibrant space for the community.

Project Updates

February 23,  2018 - Construction will begin in early May for Splashpad and Play area for 2-5 and 5-12 equipment as well as other site features.  The park will be closed May-August 2018 for construction. 

November 13, 2017 - Work begin in park to upgrade electrical panel and outlets.

August 30, 2017 - Updated plans Sent to Site Plan Review for Final Approval

July 26, 2017- Conditional Site Plan Memo sent

June 21, 2017- Conditional Site Plan Review Approval

June 6, 2017 - Site Plan Review

May 22, 2017 - Construction Documents submitted for Site Plan Review

Project Timeline & Meetings

Online survey: August 1- September 18, 2015.  (The survey is now closed. Please reference Meeting #1 notes to see the summary of survey results.)

Meetings: Design Advisory Committee Meeting #1 Wednesday, September 23, 2015 5-7pm
Neighborhood House/Wellstone Center - room 272

Meetings: Design Advisory Committee Meeting #2 Thursday, November 19, 2015 4-6pm
Neighborhood House/Wellstone Center - Room 212

Meetings: Design Advisory Committee Meeting #3, Wednesday, January 27, 2016 4-6pm
Neighborhood House/Wellstone Center - Room 212

Public Open House,  April 6, 2016  5:30--7pm Neighborhood House/Wellstone Center - Rm 212
*The Design Advisory Committee met one hour prior (4:30-5:30pm) for a public art workshop*
This will be a chance to review the current plan and timeline for moving forward.

Art Workshop,  April 13, 2017  5:00-6pm Neighborhood House/Wellstone Center - Rm 107
The public artist, Craig David, led a brainstorming and planning session for  the public art benches.


Project Resources