Snelling Avenue lane restrictions are scheduled to be removed on Friday, October 2
This week (September 28 - October 2)
- Crews poured the final sections of sidewalk.
- Permanent parking and traffic control signs were installed.
- By 5 p.m. Friday, October 2, crews are scheduled to remove lane restrictions at the intersection.
Next week (October 5-9)
- Crews will install bike racks.
- Crews will wrap up the project and remove remaining construction materials from the site.
Local and business access
- Lane restrictions on Grand Avenue and Snelling Avenue are scheduled to be lifted by 5 p.m. Friday, October 2.
- Grand Avenue reopened to through traffic on August 27.
- Grand Avenue will remain open for business access and parking.
- Some parking near the intersection may have limited access.
Pedestrian access during construction
- Pedestrian access will be maintained around the work zone to safely cross Grand Avenue and Snelling Avenue.
- Pedestrians should follow posted detour signs around the work zone.
Bus Stops and Routes
- For information see Metro Transit's webpage.
All construction activities and traffic impacts are weather and schedule permitting and subject to change.