Grand Avenue Construction Update
This week (October 20-24)
Grand Avenue between Fairview Avenue and Macalester Street:
- Installation of the center lanes, turn arrows, and crosswalks will be completed by the end of the week/early next week.
- Bike rack installation will be completed.
- Macalester College construction continues.
- Crews continue to work on the north side between Cambridge and Macalester streets.
Next week (October 27-31) and beyond
Grand Avenue between Fairview and Snelling avenues:
- The temporary 1-hour and 2-hour parking signs that were installed earlier this year will be removed later. Schedule is to be determined.
- Tree plantings are anticipated to begin in late October and continue into November. If weather or other impacts affect the schedule, this may occur next year.
- Macalester College construction continues.
- Crews continue to work on the north side between Cambridge and Macalester streets.
Pedestrian access during construction
- Pedestrians should follow any posted signs along Grand Avenue.
Bus stops
- For more information see Metro Transit's webpage.
All construction activities and traffic impacts are weather and schedule permitting and subject to change.
Grand Avenue Adjusted Schedule
Grand Avenue Continued Construction Flyer - October 24, 2025