The project is reconstructing Wheelock Parkway from Edgerton Street to Arcade Street to replace the roadway pavement, sidewalks, curbs, and underground utilities including water and sewer.
Additional project benefits:
- ADA-compliant pedestrian ramps
- Boulevard trees - to be planted after street construction
- Concrete outwalks and driveway aprons
- Lantern-style street lighting
- Private utility upgrades
- Water main upgrades
- Public art
- Sodded boulevards
- Storm sewer catch basins
Location
Wheelock Parkway from Edgerton Street to Arcade Street
Timeline
2022 - 2023
Construction is Underway
- Wheelock Parkway is closed to thru traffic.
- Please follow traffic control and No Parking signs
New Sidewalks: No Salt
Please refrain from using salt to remove ice on new concrete installed this year. Salt will harm newly installed concrete and increase freeze/thaw cycles which can do further damage.
We appreciate your assistance in helping maintain the new sidewalks.
Project Updates
-
Wheelock Parkway is anticipated to open Friday, September 1!
Please slow down and be aware of pedestrians and bicyclists using the parkway.The contractor is still utilizing construction equipment. Do not move traffic control signs and barrels.
This Week
- Completed paving
- Completed the majority of sewer televising
- Installed new street signs
- Completed sod installation
- Watered sod - please be aware of slow-moving water truck(s)
- Removal of traffic control signs is anticipated to be complete by end of the week
Anticipated Work Next Week
- Complete televising remaining sewer lines
- Continue watering sod for several more weeks - please be aware of slow-moving water truck(s)
Traffic and Pedestrian Notes
- Wheelock Parkway is anticipated to open Friday, September 1
- Please slow down and be aware of pedestrians and bicyclists using the parkway
- The contractor is still utilizing construction equipment - do not move or traffic control signs and barrels
-
This Week
- Graded and prepared topsoil for sod installation
- Installed sod within the right of way between Payne Avenue and Greenbrier Street (further project installation of sod was delayed due to the extreme heat – installation continues)
- Completed grouting manholes
- Milled joints between new/older asphalt/paving
- Televised sewer lines
Next week
- Complete sod installation
- Pave wearing course
- Complete televising sewer lines and services
- Install new signage
Traffic and Pedestrian Notes
- Sidewalks are open throughout the construction area – please be cautious and aware of construction equipment being operated
- Efforts will be made to maintain driveway access - there may be delays
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Graded behind the curb from Payne Avenue to Walsh Street
- Raised manholes and gate valves on Wheelock Parkway
- Installed sod from Payne Avenue to east of Edgerton Avenue
- Cleaned and prepped manholes for grouting
Next week
- Continue manhole preparations
- Continue grading behind the curb
- Prepare boulevards for sod installation
- Install sod from Payne Avenue east to Weide Street
- Televise sewer lines and services
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during construction
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Continued sidewalk, pedestrian ramps, and outwalks, working towards completion
- Paved bike trail within median
- Graded behind the curb within the median area
- Raised manhole and valve boxes to grade on Wheelock Parkway
- Adjusted curb stops
- Completed tabletop pedestrian crossing at Walsh Street
Next week
- Begin lining brick manholes
- Continue grading behind curb
- Continue median clean-up as work progresses
- Begin preparing boulevards for sod
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during construction
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Paved bike trail within median
- Graded behind the curb within the median area
- Raised manhole and valve boxes to grade on Wheelock Parkway
- Adjusted curb stops
- Completed tabletop pedestrian crossing at Walsh Street
Next week
- Begin lining brick manholes
- Continue grading behind curb
- Continue median clean-up as work progresses
- Begin preparing boulevards for sod
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during construction
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Completed curb and driveway-apron installation from Payne Avenue to Walsh Street
- Placing final grade of bituminous on Wheelock Parkway
- Paving Wheelock Parkway from Payne Avenue to Walsh Street
- Grading behind the median-area curb
- Installed light foundations and conduit
Next week
- Raise manholes in paved areas west of Payne Avenue
- Continue grading behind median curb
- Complete flatwork/sidewalks
- Continue median clean-up as work progresses
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during construction
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Installed curb from Payne Avenue to Walsh Street
- Continued median work, grade and gravel
- Cleaned manholes in preparation for grout and cementitious liner
- Raised trail iron and manholes
Next week
- Continue concrete and curb installations
- Continue bike trail median work
- Continue median clean-up as work progresses
- Commence paving late in the week from Payne Avenue to Walsh Street
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during construction
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
-
Completed removal of all subgrade and unsuitable soil within the roadway
-
Paved east and westbound Wheelock Parkway between Payne Avenue and Edgerton Street
-
Installed sidewalk, pedestrian ramps, and curb within Payne and Nebraska Avenues
-
Began work on the bike trail median
-
Removed remaining sidewalk and driveway-aprons
Next week
-
Continue and complete remaining curb installation, followed by sidewalk work
-
Continue bike trail median work
-
Continue median clean-up as work progresses
Traffic and Pedestrian Notes
-
Efforts will be made to maintain driveway access - there may be delays during construction
-
Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
-
Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
-
Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
-
This Week
- Continued subgrade removal from Payne Avenue to Walsh Street
- Removed unsuitable soils and unused materials and cleared storage zones off the project site
- The contractor anticipates miscellaneous work and continued project cleanup to occur on Saturday, July 8
Next week
- Continue subgrade and/or unsuitable soil removals between Walsh and Greenbrier Streets
- Begin concrete removals between Payne Avenue and Walsh Street
- Begin preparation for concrete curb, sidewalk, and driveway-apron installations between Payne Avenue and Walsh Street
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during construction
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Completed all utility, sanitary storm, and water service work
- Removed roadway subgrade from Payne Avenue to Greenbrier Street
- Replaced areas of sidewalk and pedestrian ramps within the Payne Avenue and Nevada Avenue areas
Next week
- No work occurring on Monday, July 3 and Tuesday, July 4
- Continue roadway subgrade removal between Walsh and Greenbrier Streets
- The prime contractor is anticipating work on Saturday, July 8
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during construction
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Continued storm sewer work within the Greenbrier Street intersection
- Removed subgrade material from Payne Avenue to Greenbrier Street
- Installed curb from Payne Avenue moving west
- Sprayed hydraulic soil stabilizer on last year’s construction areas where sod was not placed
- Installed conduit for lighting at Payne Avenue
Next week
- Continue storm sewer work within the Greenbrier Street intersection
- Finish concrete flat work from Payne Avenue moving west
- Continue subgrade excavation from Payne Avenue to Greenbrier Street
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during utility work
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Completed storm sewer work within the Walsh Street and Wheelock Parkway intersection
- Continued storm sewer work within the Greenbrier Street intersection
- Excavate/remove subgrade material from Payne Avenue, moving west
Next week
- Continue storm sewer work within the Greenbrier Street intersection
- Install curb from Payne Avenue, moving west
- Continue subgrade excavation between Payne Avenue and Greenbrier Street
- Install utility crossing at Payne Avenue
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during utility work
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This week
- Continued storm sewer work by Walsh Street, working west toward Greenbrier Street
- Completed infiltration trench between Arlington Avenue and Greenbrier Street
- Completed replacing lead water services between Greenbrier Street and Payne Avenue
- Completed televising sewer services completed during 2022 construction
- Completed televising sewer service work completed in 2023
- Completed/passed watermain testing
Next week
- Begin subgrade work east of Edgerton Street, working toward Payne Avenue
- Continue storm sewer work between Walsh and Greenbrier Streets
- Remove temporary water hook-ups later in the week
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during utility work
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Complete storm sewer work west of Greenbrier Street
- Begin infiltration trench between Greenbrier Street and Arlington Avenue, eastbound lane
- Replace lead water services between Greenbrier Street and Payne Avenue
- Televise sewer services completed during 2022 construction
Work Anticipated Next Week
- Continue infiltration trench between Greenbrier Street and Arlington Avenue, eastbound lane
- Continue water service work
- Begin storm sewer work between Greenbrier and Walsh Streets
- Temporary water services may be removed the following week
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during utility work
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
- Installed new storm sewer from Greenbrier Street to Payne Avenue
- Removed excess common x (clay)
- Removed topsoil in median for infiltration trench
- Tested watermain
Work Anticipated Next Week
- Begin infiltration trench between Greenbrier Street and Arlington Avenue, eastbound lane
- Continue storm sewer work
- Replace lead water services between Greenbrier Street and Payne Avenue
Traffic and Pedestrian Notes
- Efforts will be made to maintain driveway access - there may be delays during utility work
- Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
This Week
-
Completing installation of watermain, hydrants, and gate valves
-
Removed old light pole basins
Work Anticipated Next Week
-
Replace lead water services between Greenbrier Street and Payne Avenue
-
Begin storm sewer work from Greenbrier Street to Payne Avenue, as well as Walsh Street
Traffic and Pedestrian Notes
-
Efforts will be made to maintain driveway access - there may be delays during utility work
-
The sidewalk is closed between Greenbrier Street and Payne Avenue - a pedestrian access route is in-place
-
Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
Detours:
-
Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
-
Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
-
This Week
-
Installed watermain, hydrants, and gate valves
-
Continued removals of curb, bituminous (asphalt), and concrete - moving west from Payne Avenue
-
Closed sidewalk between Greenbrier Street and Payne Avenue - a pedestrian access route is in-place
-
Began tree removal between Greenbrier Street and Payne Avenue
-
Placed sod on last year’s construction phase, between Arcade and Walsh Streets
Work Anticipated Next Week
-
Begin watermain replacement at Greenbrier Street in the westbound lane of Wheelock Parkway, working toward Payne Avenue
-
Replace lead water services between Greenbrier Street and Payne Avenue
-
Possible storm sewer work starting at Walsh Street and Wheelock Parkway
Traffic and Pedestrian Notes
-
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway - please follow posted detour
-
Nevada Avenue will be closed at Wheelock Parkway beginning Monday, March 15
-
A pedestrian access route will be in-place Monday morning, east of Edgerton Street
-
-
Efforts will be made to maintain driveway access - there may be delays during utility work
-
Please do not disrupt traffic control signs - they are an essential safety measure for those navigating the construction area
Detours:
-
Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
-
Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
-
This Week
o Installed new sewer services
o Continued with removals, curb, bituminous & concrete
o Minor work on watermain in the intersection of Walsh and Wheelock Pkwy
o Sidewalk Closed between Payne Ave and Greenbrier St. Detour in placeNext Week
o Watermain shut down next Tuesday. Flyers will be handed out to residents for notification
o Monday morning Payne Ave and Wheelock Pkwy intersection will be shut down for removals
o Watermain replacement starting at Greenbrier St on the west bound lane of Wheelock Pkwy working toward Payne
o Possible storm sewer work starting at Walsh St and Wheelock Pkwy
o Last year’s phase between Arcade St and just east of Walsh St will be sodded starting next Monday
o Nevada Ave will be closed at Wheelock Pkwy starting next MondayTraffic and Pedestrian Notes
- Road closed to thru traffic at Payne Ave and Arcade St on Wheelock Parkway
- Detour:
- Traveling east on Wheelock: go north on Edgerton St to Larpenteur Ave going east to Arcade, then south to Wheelock
- Traveling west on Wheelock: go north on Arcade to Larpenteur Ave going west to Edgerton then south to Wheelock
-
Residents will be allowed access to their driveways
Project Notes
- At times there may be delays with access to driveways with utility work
- Thank you for your patience as we work to improve your neighborhood
-
This Week
-
Installed tree and inlet protection
-
Removed bituminous and concrete between Walsh Street and Payne Avenue
-
Began saw-cutting sidewalk and street
Work Anticipated Next Week
-
Continue removals
-
Begin minor watermain work in the intersection of Walsh Street and Wheelock Parkway
-
Replace sewer services at various locations
Traffic and Pedestrian Notes
-
Please do not disrupt/move traffic control signs - they are an essential safety measure for those navigating the construction area
-
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
- Efforts will be made to maintain driveway access however, there may be delays while utility work is occurring
Detours:
-
Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
-
Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
-
Work Anticipated Next Week
- Closure in both directions of Wheelock Parkway from Arcade Street to Payne Avenue
- Removal of curb and asphalt
- Installation of new watermain in the intersection of Wheelock Parkway and Walsh Street
- Replacement of sewer services anticipated the week of May 1
- Installation of sod on last season’s construction, weather and contractor-schedule permitting
Traffic and Pedestrian Notes
-
Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area
-
Road closed to thru traffic at Payne Avenue and Arcade Street on Wheelock Parkway
- Efforts will be made to maintain driveway access however, there may be delays while utility work is occurring
Detours:
-
Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
-
Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
-
The project would like to inform area residents and visitors that tree removals will be taking place next week on Wheelock Parkway between Edgerton and Greenbrier Streets.
This work will be completed by Husky Construction, Inc. (HCI) and is in preparation for next year’s phase of reconstruction.
- Most trees scheduled for removal are in the parkway median
- The project expects this work to be completed within one-to-two days
- There may be temporary disruptions to traffic to allow for safe operations
- HCI will work with residents to provide and/or maintain driveway access
- Project Inspector Brad Mikiska (651-448-0115) will be onsite to oversee operations and work with impacted persons should challenges arise
-
- The project is in winter suspension with the exception of tree removal(s) and soil stabilizer being placed. The stabilizer work has been delayed due to rain and snow as it can only be applied under suitable weather conditions. The contractor will complete this work with the watershed district’s review/approval of application conditions.
- Sod will be installed in the spring.
- The roadway is open to traffic - traffic control equipment has been removed from the project area.
-
This Week
- Installed street lighting
- Continued grading boulevard and placing topsoil
- Completed concrete work
- Paved bike trail from Weide Street to Arcade Street
- Televised and cleaned sewer lines
Work Anticipated Next Week
- Continue grading boulevard and placing topsoil
- Place final pavement layer from east of Walsh Street to Arcade Street
- Stabilize soil (hydraulic soil stabilizer) and spray topsoil
- Sod placement may occur if schedules and weather conditions are favorable
Traffic and Pedestrian Notes
Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
- Residents are allowed access to their driveways
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022
- All work is planned to be completed by the end of 2023
- Thank you for your patience as we work to improve your neighborhood!
-
This Week
- Completed bike trail grading
- Continued boulevard grading
- Installed signal loops at Arcade Street and Wheelock Parkway
Work Anticipated Next Week
- Continue boulevard grading and place topsoil
- Complete concrete sidewalk and pedestrian ramp installations
- Place final pavement layer on Tuesday, November 1
- Stabilize soil (hydraulic soil stabilizer) and spray topsoil
- Clean and televise sewer lines
Traffic and Pedestrian Notes
Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
- Residents are allowed access to their driveways
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022
- All work is planned to be completed by the end of 2023
- Thank you for your patience as we work to improve your neighborhood!
-
Project reminder to remove personal items such as landscaping/sprinkler systems, etc. from the public right of way before sidewalk construction begins.
This Week
- Completed grading road base for pavement
- Paved base layers of asphalt
- Began boulevard grading
- Began raising manholes to final grade
Work Anticipated Next Week
- Continue grading boulevard, then place topsoil
- Complete concrete sidewalk
- Continue raising manholes to final grade
- Final pavement layer to be placed on Friday, or early the following week
Traffic and Pedestrian Notes
Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway
- Residents are allowed access to their driveways
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022
- All work is planned to be completed by the end of 2023
- Thank you for your patience as we work to improve your neighborhood!
-
Project reminder to remove personal items such as landscaping/sprinkler systems, etc. from the public right of way before sidewalk construction begins.
This Week
- Began grading the bike trail in the median.
- Poured concrete sidewalk, driveway-aprons, and curb.
Work Anticipated Next Week
- Grade roadway on Monday and Tuesday, followed by roadway paving on Wednesday.
- Raise sewer manholes to final grade.
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
Project reminder to remove personal items such as landscaping/sprinkler systems, etc. from the public right of way before sidewalk construction begins.
This Week
- Completed placement of road base from Arcade to Walsh Streets.
- Pour concrete sidewalk, driveway-aprons, and curb.
- Continue sidewalk removals and place base.
Work Anticipated Next Week
- Continue pouring concrete sidewalk, driveway-aprons, and curb.
Please note: Driveways will be inaccessible for five days following completion of the concrete pours. This time is needed for the concrete to successfully cure (dry/harden). Flyers informing residents of the temporary disruption were distributed on Wednesday, October 5.
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
This Week
- Completed subgrade excavation (removing substandard soil), beginning at Arcade Street and finishing at Walsh Street.
- Hauled-in fill sand for poor soil replacement.
Work Anticipated Next Week
- Resume curb and sidewalk work.
- Remove sidewalk on the south side of Wheelock Parkway between Greenbrier and Walsh Streets.
- A reminder to remove personal items such as landscaping/sprinkler systems, etc. from the public right of way before sidewalk construction begins.
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents are allowed access to their driveways.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
This Week
- Installed new storm sewer from Walsh to Arcade Streets.
- Installed new water main in the median between Walsh and Weide Streets.
- Began subgrade excavation (removing substandard soil), starting at Arcade Street.
Work Anticipated Next Week
- Continue subgrade excavation.
- Remove sidewalk on the south side of Wheelock Parkway between Greenbrier and Walsh Streets.
- A reminder to remove personal items such as landscaping/sprinkler systems, etc. from the public right of way before sidewalk construction begins.
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents are allowed access to their driveways.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
This Week’s Work
- Installed new sanitary sewer services between Walsh and Arcade Streets.
- Installed tree protection.
- Removed sidewalk on the south side of Wheelock Parkway between Walsh and Arcade Streets.
- Removed median light poles.
- A reminder for impacted properties to remove personal items (landscaping/sprinkler systems, etc.) from the public right of way before sidewalk construction begins.
Next Week’s Anticipated Work
- Install new storm sewer on Wheelock Parkway near Arcade Street.
- Install new water main in the median, beginning at Walsh Street working east towards Weide Street.
- Install gravel for sidewalk installation on the south side of Wheelock Parkway between Walsh and Arcade Streets.
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents are allowed access to their driveways.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
This Week
- Removed existing curb and concrete pavement.
- Removed two trees in the median.
- A reminder for impacted properties to remove personal items (landscaping/sprinkler systems, etc.) from the public right of way before sidewalk construction begins.
Next Week
- Remove existing sidewalk on the south side of Wheelock Parkway between Arcade and Walsh Streets.
- Place gravel in the sidewalk area.
- Utility work is anticipated to begin this week.
- Replace sanitary services.
- Xcel Electric to remove light poles in the median.
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents are allowed access to their driveways.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
This Week
- Install sidewalk forms and place concrete.
- Mill bituminous pavement between Arcade and Walsh Streets.
Next Week
- Remove existing sidewalk on the south side between Arcade and Walsh Streets.
- Place gravel within sidewalk areas.
- Remove existing roadway material.
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents are allowed access to their driveways.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
This Week
- Excavated sidewalk and driveway areas
- Placed gravel base
- Placed forms for sidewalk installation
Next Week
- Installation of sidewalk and driveway aprons
- Mill and pave the roadway
Traffic and Pedestrian Notes
- Please do not disrupt/move traffic control signs. These signs are an essential safety measure for those working in, and those navigating around, the construction area.
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents are allowed access to their driveways.
Project Notes
- Supply chain issues remain a problem with utility work and may impact the amount of work completed in 2022.
- All work is planned to be completed by the end of 2023.
- Thank you for your patience as we work to improve your neighborhood!
-
This week
- Sidewalk and driveway-apron removals from Greenbrier Street to Arcade Street on the north side of Wheelock Parkway.
- Excavation in sidewalk areas and placement of gravel base.
Next week
- Continue sidewalk and driveway-apron removals.
- Placement of concrete sidewalks and driveway-aprons.
Traffic and Pedestrian Notes
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Larpenteur Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Larpenteur Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents will be allowed access to their driveways.
-
This Week
- Installed inlet protection.
- Performed tree removal and stump-grinding from Greenbrier Avenue to Arcade Street.
Next Week
- Begin sidewalk removals on the north side of Wheelock Parkway between Walsh and Arcade Streets.
- Possible utility work.
Traffic and Pedestrian Notes
- Road closed to thru traffic at Edgerton and Arcade Streets on Wheelock Parkway.
- Detours:
- Traveling east on Wheelock Parkway: North on Edgerton Street to Arlington Avenue going east to Arcade Street, then south to Wheelock Parkway.
- Traveling west on Wheelock Parkway: North on Arcade Street to Arlington Avenue going west to Edgerton Street, then south to Wheelock Parkway.
- Residents will be allowed access to their driveways.
Project Notes
- There are delays procuring water main pipe and manhole structures.
Project Documents
Water Main Replacement
Saint Paul Regional Water Services (SPRWS) will replace all lead water services from the water main to the property line (public right of way portion) as part of this project. If you have a lead water service from the property line to the water meter at your property (private portion), you can sign-up for SPRWS’ Lead Free Program to have this portion replaced at no cost. For additional information and to sign up for the Lead Free Program, visit www.stpaul.gov/water or call SPRWS’ Lead Free team at 651-266-6280.
As part of the road reconstruction project, SPRWS will be replacing the water main on Wheelock Parkway.
To continue to ensure the reliability of our system, SPRWS will be replacing the existing 8" cast iron water main with 8" ductile iron pipe. The scope of the main replacement work is as follows:
- Replace approximately 1,200 feet of 8" cast iron water main with 8" ductile iron
- Replace necessary valves and hydrants within the project area
SPRWS Contacts
- Project Engineer: Kaitlin Swanson 651-266-6289
- Project Inspector: Ramsey Coronado 651-266-6294