Project Map

The City of Saint Paul is developing an alley improvement program which will reconstruct one or two alleys per year and/or undertake substantial patching on a limited number of alleys; funding for alley improvements is limited.
Alleys to be reconstructed or patched are selected based on a variety of factors, including available funding, cost of improvements, existing issues, drainage issues, pavement age, pavement condition, etc.
Description
Public Works will be reconstructing the alley bounded by Selby Avenue, Laurel Avenue, Mackubin Street, and Arundel Street. The project will include removing existing brick pavers and reconstructing the alley with bituminous pavement.
Location
Alley bounded by Selby Avenue, Laurel Avenue, Mackubin Street, and Arundel Street (east-west alley in Woodland Park Addition, Block 10, Lots 1 to 24).
Timeline
2025
Thanks to everyone who joined the virtual community meeting on April 14.
View the April 14 PowerPoint that was presented during the meeting.
The project is funded through Citywide Alley Program funding and assessments to the abutting property owners:
Project Manager Bill Vos
651-266-6113
Project Engineer Cheng Xiong
651-266-6168