Overview

Parks and Recreation has received Federal and local match funding for the reconstruction of the Fish Hatchery Trail between Warner Road and Battle Creek Regional Park trailhead. The project will include trail reconstruction and widening where conditions allow, installation of site amenities such as lighting, benches, bike racks, and litter receptacles. 

Project Updates

March 25, 2024

Final plans have been submitted to the Minnesota Department of Transportation for the final review. We are awaiting an easement with the Minnesota Department of Natural Resources. Once both of those items are complete, we'll be able to advertise the project for bids. Construction would begin shortly thereafter.

October 13, 2023

We are completing some of the final items for approval of the trail plans. We anticipate advertising the project for bids after the first of the year to be ready for construction as soon as conditions allow in the spring.

July 25, 2023

During review of the construction documents, it was determined the plans could not be approved as they were. We are working through revisions to the plans and anticipate a late summer completion for final review. This will allow us to advertise the project for bids in Fall/winter and be on track for construction in the spring/summer of 2024.

May 30, 2023

Construction documents have been submitted to the Minnesota Department of Transportation for a final review. Easements are being secured with the Department of Natural Resources. We anticipate advertising for bids in June for a July bid opening. Tree clearing and ground surcharging will take place this fall and main trail construction begin in spring 2024.

March 29, 2023

We have been in the process of developing plans for the Fish Hatchery Trail project and will be on the Southeast Community Organization Land Use Committee meeting agenda April 3, 2023. The meeting will be hybrid format. In person will be held at the Conway Sports Dome facility (2080 Conway Street) and online at this zoom link: https://us02web.zoom.us/j/84824748334. The meeting will be from 6:00 - 7:30 p.m.

We are working toward a summer 2023 bid for tree clearing in the fall and construction in the spring 2024. This schedule has been established to minimize disturbance of rare species and other significant natural features such as Butternut trees, Kitten-tails, Northern Long-Eared Bat, and Rusty Patched Bumblebee.

To view the the document that was presented at the meeting, please access this Southeast Community Organization meeting document.

May 5, 2022

It will be necessary to collect additional soil borings to adequately study the structural properties of the soil in order to design the new trail. A materials testing company will be on site May 11-13 to collect soil borings along the existing and proposed trail alignment. Portions of the trail may be blocked at this time and care should be taken when using the trail. 

Last Edited: March 25, 2024