June 18, 2026 Construction Update
This week (June 22 - 26):
Construction Hours:
- Work hours planned Monday – Friday, 7 a.m. – 7 p.m.
- Phase 1 will continue through mid-summer.
University Avenue and Lafayette Road
- Phase 1 will continue at the intersection of Lafayette Road and University Avenue.
- This intersection will be closed to through access.
- Watermain installation to begin.
- Sanitary Sewer installation to begin.
- Private utility work ongoing.
University Avenue between North Pine and North John Streets:
- Remains open through mid-summer.
- Vehicle access to remain for businesses.
- Pedestrian access to remain.
- 4-way stop installation for traffic control.
University Avenue between L’Orient Street and North Pine Street:
- Phase 1 will close University Avenue between L’Orient and North Pine Streets through mid-summer.
- Pavement and pipe removals will continue.
- Private utility work ongoing.
Next week (June 30 – July 3)
**No work on Friday, July 3 in observance of July 4**
University Avenue and Lafayette Road
- Continued installation of Watermain.
- Continued installation of Sanitary Sewer.
- Private utility work ongoing.
Local and business access
- Local and business access remains open via Olive and North Pine Streets.
- Please avoid using private business property as a shortcut. It is not a through-route for public traffic, and doing so can disrupt operations and create safety concerns. Thank you for using designated routes.
Pedestrian access during construction
- Pedestrians should follow posted detour signs along University Avenue. Pedestrian access will change as crews work in the area.
- When work occurs in intersections, there will always be one north/south and one east/west crossing available.
Bus Stops
- For more information, see Metro Transit's webpage.
All construction activities and traffic impacts are weather and schedule permitting and subject to change.