Description
The City of Saint Paul plans to reconstruct University Avenue from I-35E to Lafayette Road in 2025 and 2026. The roadway is approximately ¼ mile, serves multiple modes of transportation, and provides access to several properties through a primarily industrial area.  The intersection of Lafayette Road and University Avenue is part of this work, but the design has not yet been finalized.  

Project improvements include improved curbs and pedestrian ramps, sidewalk updates, new road surface, more trees, shared use walk/bike path, new street lighting, and replacement of underground utilities as needed.

Location
University Avenue from I-35E to Lafayette Road

Timeline
2025 - 2026

University Avenue Reconstruction design map.
Tags

University Avenue Reconstruction Project Update: August 21, 2026

Additional construction closures that may impact access to the East Side of Saint Paul:

MnDOT’s East 7th Street Project Weekend Closures – August 21-24 and August 28-31

  • 7 p.m. Fri, Aug. 21 through 5 a.m. Mon, Aug. 24 East 7th Street closed in both directions between Olive Street and Kittson Street
  • 7 p.m. Fri, Aug. 28 through 5 a.m. Mon, Aug. 31 East 7th Street closed in both directions between Payne Avenue and Lafayette Street.
  • 9 p.m. Fri, Aug. 28 through 5 a.m. Mon, Aug. 31 ramp from northbound Highway 52 to East 7th Street will be closed.
  • For more information, visit MnDOT’s East 7th St. and Arcade St. project webpage.
University Avenue Detour Map 8-14-26

Printable Map

Current Traffic Impacts:

  • University Avenue remains closed between L’Orient and Olive Streets.
  • The intersection of Lafayette Road and University Avenue remains closed.
  • Pedestrian access may change as work progresses. Please follow posted signage.
  • Local and business access remains open. Please follow posted signage.

Upcoming Work – Week of August 24

  • Continued work for the underground stormwater system near the intersection of Lafayette Road and University Avenue.
  • Roadway work will continue between Mississippi and E 12th
  • Sewer work will continue from Mississippi to Olive Street.

Bus Stops

All construction activities and traffic impacts are weather and schedule permitting and subject to change.

Eastside Access Map

Eastside Access Map 8/14/26

Construction Hours:

  • Work hours planned 7AM – 7PM, Monday – Saturday.
  • Thank you for your continued patience while this crucial and necessary work is being completed.

Project Contacts:

University Avenue Reconstruction Community Meeting on Tuesday, May 26, 2026

Thanks to everyone who joined Public Works on May 26 to learn more about the University Avenue Reconstruction Project. If you were unable to attend, you can view the presentation slides below.

University Avenue Presentation Slides

Public Works has hired a contractor for the full reconstruction of University Avenue from just west of I-35E to Lafayette Road.  Construction for this project is anticipated to start in June 2026. The roadway is approximately ¼ mile, serves multiple modes of transportation, and provides access to several properties through a primarily industrial area. A letter will be sent to property owners with properties abutting University.

Project Updates

Investing in Saint Paul Streets: Common Cent 

A portion of this street reconstruction project will be paid for by a 1% local option sales tax, called Common Cent. This sales tax was approved by Saint Paul voters in November 2023. A portion of the project will also be funded through assessments to property owners adjacent to the project. The estimated assessment rate is based on a third-party special benefit analysis of the property values in the project area. Property owners will receive a notice of the estimated rate and date for a public hearing when estimated rates are available. More information on assessments can be found at www.stpaul.gov/specialassessments.