Description
The City of Saint Paul will be working with a contractor to make necessary sewer repairs throughout the City. These projects are funded by the sewer utility. There are no assessments to property owners.

Streets may be closed and no parking signs posted during sewer work.

Locations

  • Wabasha Street between Congress Street and Winifred Street
    • Sewer work completed; final pavement restoration in spring/summer 2023
  • Minnesota Street at 9th Street and 11th Street
    • Work completed
  • Sumac Street and Butternut Avenue
    • Sewer work completed; some additional restoration work to be completed spring/summer 2023
  • Woodlawn Avenue South and Ford Parkway
    • Work started the week of March 13 and to be completed by June 30, 2023
  • Highland Parkway between Woodlawn Avenue and Mississippi River Boulevard
    • Work started the week of March 13 and to be completed by June 30, 2023
  • West 7th Street and Montreal Avenue
    • Work completed
  • Elway Street south of West 7th Street
    • Work completed
  • St Paul Yacht Club parking lot
    • Work completed
  • Ohio Street between Alice/Winifred and Cherokee Avenue
    • Work completed
  • Pelham Boulevard and Mississippi River Boulevard
    • Work completed
  • Mississippi River Boulevard near Magoffin Avenue - 3 work sites along west side of Mississippi River Boulevard
    • Sewer work completed; final pavement restoration in spring/summer 2023
  • Mississippi River Boulevard near Itasca Avenue
    • Sewer work is anticipated to be completed by May 31, 2023; final pavement restoration in spring/summer 2023
  • Mississippi River Boulevard near Elsie Lane
    • Sewer work is anticipated to be completed by May 31, 2023; final pavement restoration in spring/summer 2023
  • Mississippi River Boulevard north of Cleveland Avenue South
    • Sewer work is anticipated to be completed by May 31, 2023; final pavement restoration in spring/summer 2023
  • Shepard Road and Homer Street South
    • Anticipated to start in June 2023
  • Minnehaha Avenue between Kennard Street and McKnight Road
    • Work completed

Timeline
December 12, 2022 to December 2023

Tags