Description
The Capital City Bikeway will be extended along Wabasha Street to the Capitol in 2027. This project will extend the existing Wabasha Street bikeway to 10th Street, cross Interstate 94 on St Peter Street, and connect with the Capitol grounds on 12th Street. The bikeway will connect with the John Ireland Boulevard bike lanes and the planned bikeway on Rice Street. 

Wabasha CCB Extension to the Capitol map image.

The streets in the project area will be reconstructed to replace the roadway pavement, sidewalks, curbs, and underground utilities. 

Download the Project Flyer 

Location

  • Wabasha Street from 7th Street to 11th Street
  • 10th Street from Wabasha Street to St Peter Street
  • St Peter Street from 10th Street to 12th Street
  • 12th Street from St Peter Street to John Ireland Boulevard

Timeline

  • 2025 – Concept Design and Community Engagement
  • 2026 – Finalize Street Design and Utility Work
  • 2027 – Construction
Tags

Virtual Meetings on December 1, 2026

Join us virtually to learn more about the project. There will be a short presentation followed by time to ask questions about the project and construction. Both meeting times will feature the same presentation.

Tuesday, December 1
12:00 - 1:00 p.m. and 5:30 - 6:30 p.m. (same presentation at each time)

Join online via Microsoft Teams (No need to download Microsoft Teams. Join in the web browser of your choice.)

Call in (audio only): Call 612-315-7905 and enter conference ID 442 765 579#

Learn more: Recorded Presentation (Coming Week of November 2, 2026)

A recorded presentation about the Wabasha/St Peter Capital City Bikeway and Street Reconstruction project will be available online here the week of November 2, 2026. Sign up for email updates (below) to be notified when the presentation is posted online.

Project Schedule

  • COMPLETE Summer - Fall 2025: Phase 1 Community Engagement. Develop corridor goals and project concepts using feedback from the community, policy and guidance from adopted plans, and technical engineering constraints.
  • COMPLETE Fall - Winter 2025: Phase 2 Community Engagement. Throughout the months of October, November, and December 2025 the project team refined the preferred concept design and finalized the design layout. The bikeway extension's design was informed by feedback from summer and fall 2025 engagement, and technical engineering constraints.
  • UPCOMING Fall - Winter 2026: Utility Work. In preparation for the Wabasha Bikeway Extension construction, the City of Saint Paul is anticipating utility work to begin in 2026. Xcel Energy plans to complete the work moving from the north end of the corridor to the south. Expect lane reductions as work progresses with traffic flow being maintained throughout the project corridor. 

Next Phases of Work 

  • Fall - Winter 2026: Xcel Energy will be completing utility work to prepare for the Wabasha Bikeway Extension construction. Please plan for traffic impacts due to lane reductions throughout the project corridor.
  • Spring - Fall 2027: Bidding and Construction. The reconstruction of Wabasha/St Peter will take most of spring, summer, and fall. City staff will provide regular updates to the community about construction impacts, detours, and progress.

Historical Sites on the Corridor

The corridor features several historical sites that contribute to the character of downtown Saint Paul. The project team is committed to being mindful of the potential impacts on these landmarks. We welcome public input to help prioritize what matters most when considering changes to the roadway. Historic sites along the corridor include:

  • New Astor Theater
  • Eisenmenger Meat Market
  • Fitzgerald Theater (formerly the Sam S. Schubert Theater)
  • Minnesota Arts & Sciences Center
  • History Theatre building
  • Twin Cities Rapid Transit Company Building
  • Colonnade Hotel
  • Minnesota State Capitol Mall Historic District
  • State Veterans Services Building

Project Goals

Graphic showing the Wabasha CCB Extension project goals.

2025 Engagement Completed

Capital City Bikeway Open House Materials

Thank you to everyone who attend the Capital City Bikeway Open House on October 23, 2025 at the Minnesota History Center. At the event, staff answered questions and presented the preferred concept design for Wabasha/St Peter. Review the materials here: 

Curious about our survey?

The survey closed as of November 27, 2025. If you would like to know what questions we asked about the preferred concept and design alternatives, check out the survey link below.

Survey

Project Documents