Description
Road improvements to address drainage issues. Improvements included:

  • Concrete curb and gutter on north side
  • Sidewalk reconstruction on north side
  • Sewer and water main replacement or repair
  • Roadway pavement

Location
Curtice Street East between Woodbury Street and Andrew Street

Timeline
July 2023 to October 2023

Tags

    Project Updates

    Water Main Replacement

    As part of the road reconstruction project, Saint Paul Regional Water Services (SPRWS) replaced the water main on Curtice Street. The scope of the main replacement work was as follows:

    • Replaced approximately 1,100 feet of 6" cast iron water main with 8" ductile iron
    • Replaced necessary valves and hydrants in the project area

    SPRWS contacts