Earl Street Reconstruction Phase 1 Project Update: October 30, 2026
Construction work hours are 7 a.m. - 7 p.m. daily. Workers may be on-site and working up until 7 p.m. on a given day. Weekend work may also occur through the remaining construction season.
Work This Week (October 26 - 30):
- Earl Street between Maryland Avenue to Magnolia Avenue – Finishing curb and gutter, paving driveways, and removing sidewalks.
- Earl Street between Magnolia Avenue to Case Avenue – Preparing base of roadway.
- Earl Street between Cook Avenue to York Avenue – Finishing removal and installation of storm sewer.
- Case Avenue and Jenks Avenue – Testing infiltration trenches.
- Weekend work will continue this week through Sunday, November 1.
Work Next Week (November 2 - 6):
- Earl Street between Maryland Avenue to Magnolia Avenue – Paving sidewalks.
- Earl Street between Magnolia Avenue to Case Avenue – Constructing curb and gutter and paving bottom layer of asphalt.
- Earl Street between Case Avenue and York Avenue – Preparing base of roadway and constructing curb and gutter.
- Case Avenue and Jenks Avenue – Constructing infiltration trenches.
Safety Topic:
- Pedestrian access along Earl Street will be restricted in areas of removal and paving sidewalks, use Cypress Street or Frank Street for the short-term restrictions.
- Pedestrian access along Case Avenue and Jenks Avenue will be restricted for safety near trench excavations.
- Earl Street closed to traffic from Maryland Avenue to York Avenue.
All construction activities and traffic impacts are weather and schedule permitting.
Eastside Access Map
All construction activities and traffic impacts are weather and schedule permitting and subject to change.