Project Details
Description
The City of St Paul is replacing the Kellogg-3rd Street bridge to address the need for a more reliable connection to the City that will accommodate people walking, biking, taking transit, and driving.
Location
Kellogg-3rd Street bridge including Kellogg Boulevard from Broadway Street to Mounds Boulevard.
Timeline
- Kellogg-3rd Street bridge closed July 29, 2024.
- Kellogg-3rd Street bridge is expected to open in 2027.
- Anticipated project schedule is shown below. All dates are subject to change.
View a short video update of pouring the concrete deck for the Kellogg-3rd Street bridge - June 2026
View a short video update on the Kellogg-3rd Street bridge construction - Fall 2025
Construction Update & Detours
- Concrete bridge deck is complete. The deck was poured in 9 separate events over a span of two months. Each pour lasted over 10 hours and required around 800 cubic yards of concrete (80 ready-mix cement trucks).
- The contractor (Lunda) is now pouring concrete barriers on the new bridge deck. This work will continue through summer. The project includes nearly two miles of barriers that will protect vehicle and non-motorized traffic.
- Other ongoing work on site includes installation of lighting and storm sewer.
Watch the Kellogg-3rd Street Bridge deck being poured
Photos of the concrete deck being poured on April 22, 2026.
Kellogg-3rd Street Bridge Closure Traffic Impacts and Detour Routes
For other downtown construction and traffic impacts, visit stpaul.gov/roadclosures.
Traffic Impacts
- Kellogg-3rd Street Bridge will be closed for approximately three years.
- Vehicles will be detoured to East 7th Street. See map for details.
- Kellogg Boulevard between Broadway and Lafayette will be closed to traffic for reconstruction starting July 29, 2024 through November 2024.
- Access to parking lots will be maintained. See detailed maps below.
- Traffic delays should be expected.
Pedestrian and Bike Impacts
Two detours are posted for pedestrians and bikes:
Parking Lot and Business Access
- Parking lots, buildings, and Union Depot will remain accessible during construction from Lowertown on the west side of the bridge. See detailed maps below to access parking lots.
- Owners and tenants immediately adjacent to the work site will receive separate notices during specific work activities that may affect their property.
Detour map for Kellogg-Third Street Bridge construction
Note Robert Street is closed for construction. Traffic is being detoured to Jackson Street southbound and Minnesota Street northbound to 7th Street.
Printable detour map for Kellogg-Third Street Bridge construction
Area closures and restrictions in Downtown Saint Paul, August 21, 2026
Construction is happening throughout downtown. Plan accordingly and expect delays. Please follow all posted signs. Road and lane closures will change as construction continues.
Additional construction closures that may impact access to downtown Saint Paul:
MnDOT’s East 7th Street Project Weekend Closures – August 21-24 and August 28-31
- 7 p.m. Fri, Aug. 21 through 5 a.m. Mon, Aug. 24 East 7th Street closed in both directions between Olive Street and Kittson Street
- Detour map: Olive St., 8th St., Pine St., Grove St., Olive St., Phalen Blvd, Payne Ave. (PNG)
- Overnight work through 6 a.m. Sat, Aug. 22.
- Eastbound East 7th St. to southbound Hwy 52 remains open to eastbound traffic only using Olive St., 8th St., and Lafayette St.
- 7 p.m. Fri, Aug. 28 through 5 a.m. Mon, Aug. 31 East 7th Street closed in both directions between Payne Avenue and Lafayette Street.
- 9 p.m. Fri, Aug. 28 through 5 a.m. Mon, Aug. 31 ramp from northbound Highway 52 to East 7th Street will be closed.
- For more information, visit MnDOT’s East 7th St. and Arcade St. project webpage.
For Saint Paul Public Works projects and links to other agencies and their projects, visit www.stpaul.gov/Construction.
For current and upcoming road closures in Saint Paul, visit www.stpaul.gov/RoadClosures.
There will be some short-term lane restrictions due to window washing and roofing on private buildings.
See below for a map of the road closures and restrictions as of August 24, 2026.
- 5th Street: Lane restrictions between Wabasha and Cedar streets for Wabasha Park (formerly Osborn Plaza).
- West 7th Street: Lane restrictions between Walnut Street and Kellogg Boulevard on West 7th for sewer work.
- East 7th Street:
- Lane restrictions between I-94 and Minnehaha Avenue on East 7th for MnDOT work. One lane in each direction.
- August 21-24 and August 28-31, weekend closures of East 7th Street. See text at start of email. For more information, visit MnDOT’s East 7th St. and Arcade St. project webpage
- 9th Street: Eastbound closed between Temperance and Sibley.
- Chestnut Street: Closed at West 7th Street for sewer work.
- Eagle Parkway:
- Starting Monday, August 24, Eagle Parkway from Shepard Road to Chestnut Street will have lane restrictions and be reconfigured to one lane in each direction for Xcel Energy electric work.
- Access to northbound Eagle Parkway will only be from eastbound Shepard Road.
- Southbound vehicles on Eagle Parkway will be able to go both east and westbound on Shepard Road.
- Jackson Street:
- Monday, August 24, Jackson Street north of University Avenue will be closed at University Avenue for sewer work.
- Thursday, August 27, Jackson Street between Kellogg Boulevard and Shepard Road is scheduled to open with one lane southbound to eastbound Shepard Road. For more information, visit the city’s Lowertown Floodwall webpage.
- August 29-30, Jackson Street between 7th Street and 7th Place will be closed to all traffic.
- John Ireland Bridge: Closed for MnDOT reconstruction.
- Kellogg Boulevard:
- Westbound lanes closed between West 7th Street and Wabasha Street. Eastbound open with two lanes between West 7th Street and Wabasha Street. For more information about the CCB Kellogg Phase 2 project, visit stpaul.gov/ccbkellogg2.
- Kellogg Boulevard/3rd Street bridge remains closed through 2027. Kellogg Boulevard remains closed between Lafayette Street and Mounds Boulevard. For more information about the Kellogg/3rd Street Bridge project, visit: stpaul.gov/Kellogg-3.
- Lafayette Road: Road closed to all thru traffic at University Avenue.
- Shepard Road:
- Westbound Shepard closed between Eagle Parkway and Sibley Street.
- Shepard Road closed to thru traffic at I-35E for MnDOT bridge reconstruction.
- Eastbound will remain open from I-35E to Highway 61.
- Eastbound Shepard traffic can access downtown from Eagle Parkway and Sibley Street (no trucks due to bridge height).
- Westbound Shepard traffic can access downtown from Sibley Street, except no trucks due to bridge height.
- On August 23, the West 7th Street ramp will close again, and the Shepard Road ramp to southbound I-35E will reopen. The West 7th Street ramp will remain closed through this fall.
- For more information, visit MnDOT's I-35E and Shepard Road webpage.
- Temperance Street: Lane restrictions between 7th and 9th streets for roofing work.
- University Avenue: Road closed between Lafayette Road and L’Orient Street. Access to businesses is being maintained. See access map at www.stpaul.gov/UniversityAvenue
- Wacouta Street: Lane restrictions between 6th and 7th streets and 4th and 5th streets for Xcel Energy work. Southbound traffic only.
- Washington Street: Road closed between 6th and 5th Streets.
NOTE: All construction activities and traffic impacts are weather and schedule permitting and subject to change.
Downtown Construction & Access Map for Monday, August 24, 2026
Project Updates - 2026
Project Updates - 2025
Project Updates - 2024 and earlier
Final Art Designs
View the final art designs on the railings and pier columns, including the specific locations.