Project Details
Description
The City of St Paul is replacing the Kellogg-3rd Street bridge to address the need for a more reliable connection to the City that will accommodate people walking, biking, taking transit, and driving.
Location
Kellogg-3rd Street bridge including Kellogg Boulevard from Broadway Street to Mounds Boulevard.
Timeline
- Kellogg-3rd Street bridge closed July 29, 2024.
- Construction is anticipated to last approximately three years.
- Anticipated project schedule is shown below. All dates are subject to change.
 
View a short clip of the July 29, 2024 Mayor's Press Conference with overhead footage of the bridge
Overall Project Updates
- Project is 50% complete:- Demolition completed Summer 2025
- Foundations and Bridge Supports are ~90% complete
- Beam deliveries continue, ~50% of beams are set
- Decking, railings and lighting will be constructed in 2026
- Final project completion in Summer 2027
- Kellogg Boulevard (Broadway to Lafayette) was rebuilt in Fall 2024
- Bridge work continues (Lafayette to Mounds) 
 
Upcoming Construction Work and Impacts
- Beam deliveries will continue through January 2026- Beams will be delivered via I-94 to Kellogg Boulevard (see map #1 below)
- Beam deliveries will result in very short-term traffic impacts, including a ~5-minute closure of Kellogg Boulevard between 7th Street and Market Street in front of Xcel/RiverCentre
- 88 beams will be delivered
 
- East Abutment near Mounds Boulevard is under construction
- Piling driving activities (foundation work) will continue through November 2025, and will produce noise and vibrations
- Noise will be limited to the hours of 7 a.m. to 7 p.m. Monday through Friday
- Vibrations will be monitored to prevent damage to roads, houses, and nearby infrastructure
- Traffic lanes will be reduced on eastbound Mounds Boulevard
 
 
For other downtown construction and traffic impacts, including a weekly map of road closures and lane restrictions, visit stpaul.gov/downtownprojects.
Detour Routes
Traffic Impacts
- Kellogg-3rd Street Bridge will be closed for approximately three years.- Vehicles will be detoured to East 7th Street. See map for details.
 
- Kellogg Boulevard between Broadway and Lafayette will be closed to traffic for reconstruction starting July 29, 2024 through November 2024.- Access to parking lots will be maintained. See detailed maps below.
 
- Traffic delays should be expected. 
Pedestrian and Bike Impacts
- Two detours are posted for pedestrians and bikes:   
Parking Lot and Business Access
- Parking lots, buildings, and Union Depot will remain accessible during construction from Lowertown on the west side of the bridge. See detailed maps below to access parking lots.
- Owners and tenants immediately adjacent to the work site will receive separate notices during specific work activities that may affect their property.
Detour map for Kellogg-Third Street Bridge construction
Note Robert Street is closed for construction. Traffic is being detoured to Jackson Street southbound and Minnesota Street northbound to 7th Street.
Printable detour map for Kellogg-Third Street Bridge construction
 
Project Updates - 2025
Project Updates - 2024 and earlier
Virtual Meeting Held on June 26
Thanks to everyone who attended the virtual meeting. On June 26, 2024, Saint Paul Public Works bridge staff shared a short presentation and answered any questions. Here are the materials shared:
Final Art Designs
View the final art designs on the railings and pier columns, including the specific locations.
 
 
 
 
 
 
 
 
 
 
 
 
