The City of St Paul is replacing the Kellogg-3rd Street bridge to address the need for a more reliable connection to the City that will accommodate people walking, biking, taking transit, and driving.

Location
Kellogg-3rd Street bridge including Kellogg Boulevard from Broadway Street to Mounds Boulevard.

Timeline

  • Kellogg-3rd Street bridge closed July 29, 2024.
  • Kellogg-3rd Street bridge opened November 13, 2026.

Video of the October 24, 2026 Community Celebration and Ribbon Cutting for the Kellogg-3rd Street Bridge

View a short video update of pouring the concrete deck for the Kellogg-3rd Street bridge - June 2026

View a short video update of beam installation over I-94 for the Kellogg-3rd Street bridge - February 2026

View a short video update on the Kellogg-3rd Street bridge construction - Fall 2025

Tags

Kellogg-3rd Street Bridge is Open!

  • The Kellogg-3rd Street Bridge is open to pedestrians, bicyclists, and vehicles as of the afternoon of November 13, 2026. 
  • Final construction and punch list will continue into the winter and lane restrictions may be needed.

Watch the Kellogg-3rd Street Bridge deck being poured

Photos of the concrete deck being poured on April 22, 2026. The deck was poured in 9 separate events over a span of two months. Each pour lasted over 10 hours and required around 800 cubic yards of concrete (80 ready-mix cement trucks).

Construction crew in high visibility vests spreading concrete on the new Kellogg-3rd Street bridge on April 22, 2026.
Crews in high visibility vests spreading concrete being poured on the Kellogg-3rd Street bridge on April 22, 2026

This is the last downtown construction update for this construction season. Email updates will continue in spring 2027 when the majority of construction starts or as needed throughout the winter. For road closures in Saint Paul, please visit www.stpaul.gov/RoadClosures.

Area closures and restrictions in Downtown Saint Paul for the week of November 23, 2026

The majority of street reconstruction work is wrapping up for 2026. Utility and private construction along with clean up work on projects continues in downtown Saint Paul. Please follow all posted signs as road and lane closures are likely to change.

See below for a map of the road closures and restrictions as of November 23, 2026.

  • 5th Street: Lane restrictions between Cedar Street and Minnesota Street for private utility work.
  • 6th Street: Lane restrictions between Sibley Street and Wall Street for private building work.
  • West 7th Street: Lane restrictions between Chestnut Street and Kellogg Boulevard on West 7th for private sewer work.
  • 8th Street: Closed between Temperance and Sibley for roofing work. 
  • 9th Street: Eastbound closure between Temperance and Sibley. 
  • 10th Street: Lane restrictions between St Peter Street and Wabasha Street for Xcel Energy work.
  • Eagle Parkway:  
    • Eagle Parkway from Shepard Road to Chestnut Street has one lane in each direction for Xcel Energy electric work. 
    • Access to northbound Eagle Parkway will only be from eastbound Shepard Road.
    • Southbound vehicles on Eagle Parkway will be able to go both east and westbound on Shepard Road. 
    • More information at xcelenergystpaulsystemimprovements.com.
  • Jackson Street: Jackson Street between Kellogg Boulevard and Shepard Road is open to eastbound Shepard Road.
  • Lafayette Road: Limited access as construction wraps up for 2026. More information about the University Avenue Reconstruction project at www.stpaul.gov/UniversityAvenue. 
  • Saint Peter Street: Lane restrictions between 11th Street and Exchange Street for Xcel Energy work.
  • Shepard Road:
  • Westbound Shepard closed between Eagle Parkway and Sibley Street. More information at xcelenergystpaulsystemimprovements.com.
  • Shepard Road closed to thru traffic at I-35E for MnDOT bridge reconstruction. For more information, visit MnDOT's I-35E and Shepard Road webpage: www.dot.state.mn.us/metro/projects/i35estpaul-lilydale.
  • Eastbound will remain open from I-35E to Highway 61.
  • Eastbound Shepard traffic can access downtown from Eagle Parkway and Sibley Street (no trucks due to bridge height).
  • Westbound Shepard traffic can access downtown from Sibley Street, except no trucks due to bridge height. 
  • Sibley Street: Lane restrictions from 5th Street to 7th Place for private building work.
  • University Avenue: Limited access between Lafayette Road and L’Orient Street. Access to businesses is being maintained. More information at stpaul.gov/UniversityAvenue
  • Wacouta Street: Lane restrictions between 6th and 7th streets for Xcel Energy work. Southbound traffic only. 

NOTE: All construction activities and traffic impacts are weather and schedule permitting and subject to change. 

For Saint Paul Public Works projects and links to other agencies and their projects, visit www.stpaul.gov/Construction. 

For current and upcoming road closures in Saint Paul, visit www.stpaul.gov/RoadClosures. 

There may be some additional short-term lane restrictions due to utility work or work on private property. 

Downtown Construction & Access Map for week of November 23, 2026

Map showing road closures and lane restrictions in downtown Saint Paul for week of November 23, 2026

Kellogg-3rd Street Bridge Community Celebration & Ribbon Cutting October 24

Thanks for everyone who joined us on Saturday, October 24 for a Community Celebration and Ribbon Cutting Ceremony for the Kellogg-3rd Street Bridge as construction nears completion.

Video of the October 24, 2026 Community Celebration and Ribbon Cutting for the Kellogg-3rd Street Bridge

The new Kellogg-3rd Street Bridge is anticipated to open to vehicles, pedestrians, and bicyclists by November 15, 2026. To open the bridge as soon as possible, residents should anticipate construction activities to continue into 2027, including installing railing in some locations, landscape restoration, and other clean up activities. 

Press Release for Kellogg-3rd Street Bridge Community Celebration

Video of Kellogg-3rd Street Bridge Construction and Invite to Community Celebration

Kellogg-3rd Street Bridge Community Celebration 2026

Project Updates - 2026

Project Updates - 2025

Project Updates - 2024 and earlier

Final Art Designs

View the final art designs on the railings and pier columns, including the specific locations.

Final art designs for the Kellogg-3rd Street Bridge showing all five railing panel designs from west to east: Lowertown buildings, wild rice and river, swimming smallmouth bass, flying eagle, Dayton's Bluff buildings,
Kellogg/3rd Street Bridge Art Designs

Frequently Asked Questions