Overview

The master plan for Hidden Falls Crosby Farm Regional Park was adopted in June 2019. Since adoption, staff are searching for and exploring ways to fund improvement projects. As funding and opportunities become available through grant options and partnerships, the Department of Parks and Recreation will implement priority improvement projects identified and will communicate with the public. (See Master Plan Website)

If you have any questions or concerns regarding this project, please contact the project manager at the bottom of this page.  


Project Status

Significant Flooding occurred from May-September 2019, resulting in deposition of silt within the park and substantial coverage of recreational trails. Please be advised when using trails to be safe and be aware there may be construction traffic in this area.

Flood Emergency Management Agency (FEMA) has allocated funds to address the silt deposition at Hidden Falls Crosby Farm Regional Park. The response plan is currently planned to occur in two phases:

PHASE I:  Parks and Recreation Operations staff are working with contractors to remove excessive silt in the western area of Crosby Farm Park and along trails adjacent to the South Parking Lot in Hidden Falls Park. The silt will be deposited in the South Hidden Falls Parking Lot in anticipation of Phase II.

PHASE II:  Reconstruction of the parking lot to reduce the amount of impervious surface and reconstruct trails to increase connection and recreational opportunities per the Master Plan recommendations for Hidden Falls Park South. Phase II construction documents are complete and ready to bid in early 2021. Stay tune for future updates!

Anticipated Schedule

*Schedule Updated November 2020

  • December 2019-June 2020 - Phase I - Silt Removal in Hidden Falls and Crosby Farm Regional Park
  • Fall-Winter 2020 - Complete Phase II Construction Documents
  • Early 2021 - Bid Hidden Falls Regional Park Phase II Project
  • Spring 2021-Summer 2021 - Construction of new trails and parking lot in Hidden Falls Regional Park at the South Entry