Ongoing activities on Robert Street, updated October 18, 2024
Utility work continues through spring 2024 on Robert Street between 11th and 7th Streets and through December 2024 between 7th Street and Kellogg Boulevard in advance of the reconstruction project. Please be aware of the following impacts:
Traffic Impacts
- Robert Street remains reduced to one lane in each direction between 11th Street and Kellogg Boulevard. Intersection restrictions/closures will occur periodically as needed for safety reasons or as required to complete construction activities.
Current activities along Robert Street:
- Between 11th and 9th Streets
- Xcel Gas is working on their utilities.
- Work between 10th and 11th Street will wrap up next week.
- Work began on the 9th Street block this week.
- Between 9th and 7th Streets
- Xcel Electric is working on their underground vaults.
- Current activities scheduled in this area will continue through December 2024.
- At 7th Street
- Xcel Electric is working at the intersection
- Travelers on 7th Street, please pay extra attention as the driving lanes have switched to the south side of the intersection.
- At 6th Street
- Reduced to one lane across Robert Street.
- Between 6th Street and Kellogg Boulevard
- Xcel Gas is working on their utilities.
- Ongoing activities between 5th Street and Kellogg Boulevard will be completed next week. Crews will continue working up the corridor.
- Access to local businesses is being maintained.
Pedestrian Access
- Pedestrian access to properties on Robert Street is being maintained.
- Please follow signed pedestrian routes when walking or rolling near work zones.