Pelham Boulevard Reconstruction Project Update: August 28, 2026
Please note: In order to streamline resident comments, concerns, and feedback, please send messages to publicworksinfo@ci.stpaul.mn.us or call 651-266-6100.
Traffic Impacts
- Construction work hours are 7 a.m. - 7 p.m. daily. Workers may be on-site and working up until 7 p.m. on a given day. Weekend work may also occur through the remaining construction season.
- Intermittent closures of St Anthony Avenue and Doane Avenue will occur when sewer and water work is occurring. Closures will not occur simultaneously.
- Pelham Boulvevard is still closed.
- Mississippi River Boulevard is closed and is being used for trucking materials in and out, so please be mindful when in the area.
- Current detour is on Franklin Avenue, University Avenue, Vandalia Street/Cretin Avenue, and Marshall Avenue.
- Homes on Pelham Boulevard between Beverly Road and Otis Avenue will continue to have access but expect disruption and exercise caution when navigating active site.
- Parking will not be allowed within the construction area.
- Bike, pedestrian, and driver detours are posted according to the above detour routes. These may change throughout the project and signs will be adjusted. Printable maps are available at stpaul.gov/pelham
- Pedestrians and cyclists are to follow detours posted at St Anthony Avenue and Mississippi River Boulevard as Pelham Boulevard is CLOSED to all cyclists, pedestrians, and vehicles.
This Week (August 24 - 28)
- Sanitary sewer work was completed through the Intersection of Doane Avenue and from I-94 to Wabash Avenue.
- Remaining sanitary service repairs will be completed early next week.
- Water main installation from Beverly Road to Doane Avenue was completed through the intersection of Doane Avenue.
- The road has been graded out from Mississippi River Boulevard to Otis Avenue and from Otis Avenue to Beverly Road.
- There is a section that still needs to be graded between Otis Avenue and Beverly Road following storm sewer work, which will happen early next week.
- Sidewalk placement has begun on the east side of Pelham Boulevard between Mississippi River Boulevard and Beverly Road. Boulevard restoration has started where applicable, adjacent to the sidewalk.
Next Week (August 31 - September 4)
- Storm sewer work between Beverly Road and Doane Avenue will begin.
- Sanitary service repairs and some sanitary manhole replacements will be done between Doane Avenue and St Anthony Avenue.
- Water main installation up to St Anthony Avenue will be completed.
- Curb and gutter will be placed from Mississippi River Boulevard to Desnoyer Avenue in the early part of the week.
- Some sewer work will tentatively begin between Wabash Avenue to Myrtle Street.
Construction Communications
- In order to streamline resident comments, concerns, and feedback, please send messages to publicworksinfo@ci.stpaul.mn.us.
- Project contact is Tom Higbee 651-356-1569 for any day-to-day, on-site concerns.
- Updates will be provided weekly on Friday to inform you of progress and expectation for following week.
- Since June 24, project staff continue to host in-person, weather-permitting meetings at Desnoyer Park on Wednesdays from 3:00 p.m. to 4:00 p.m. Attendance is not mandatory and project staff will continue to answer questions via phone or email throughout the duration of construction.
Vibration Monitoring
- On Friday, August 21, Saint Paul Public Works had three vibration monitoring devices installed along the project corridor.
- The reconstruction work happening on Pelham Boulevard aligns with typical construction activities across the city.
- Vibration monitoring is not a standard part of most construction projects; however, the city is adding monitoring due to some resident concerns.
- On Friday, August 21, Saint Paul Public Works had three vibration monitoring devices installed along the project corridor.
All construction activities and traffic impacts are weather and schedule permitting and subject to change.
Pelham Boulevard Bike and Pedestrian Detour