Project Overview

Following the renovation of the Taylor Park Play Area in the fall of 2025, the Saint Paul Parks and Recreation Design & Construction team has secured additional funding to make improvements to the site's accessibility. 

This project will include a new trail loop, the replacement of the non-ADA-accessible entries with ADA-accessible ones, parking improvements including an ADA-Van-Accessible parking space, benches, picnic tables, and new park signage.
 

Project Updates

August 17th, 2026

After a handful of community members reached out to the project team requesting that the portion of the trail from the parking area to the northeast corner of the site remain, the project team has reevaluated the construction budget and determined that we do have sufficient funding to repair that path so that it can remain.

 An updated graphic is included below:


August 11th, 2026

The contractor expects to begin installing tree protection fencing and erosion control measures at the Taylor Park project site on Thursday, August 13th, 2026. Demolition is expected to begin in earnest on Monday, August 17th, 2026. Construction is estimated to take 4-6 weeks.

Check out the graphic below to see the proposed trail layout:


 

Contact Us

Project Manager

Meredith Ver Steeg
Saint Paul Parks and Recreation 
Design & Construction Division
P: (651) 266-6695
Meredith.Ver.Steeg@ci.stpaul.mn.us
 

Project Address

2131 S Howard Street
Saint Paul, MN