Project Overview

Staff are beginning work on Phase 2 of the site improvements at the Hazel Park Recreation Center. Work for this project will focus on safety and accessibility upgrades on the west and south sides of the recreation center building including improvements to pavement, stairs/ramps, and railing. Other improvements may include basketball court resurfacing, new site furnishings, and landscaping as funding allows. This project is funded through the Community Development Block Grant (CDBG) program.

Preliminary Project Schedule
Date
Phase
Jan 2026 - Mar 2026Project Start, Design Development
Apr 2026 - May 2026Construction Documents
Jun 2026 - Jul 2026Bidding/Permitting
Aug 2026Construction start (pending bids and weather
Fall 2026Target Opening Date