City of Saint Paul Parks and Recreation Department received funding to design and improve the existing Como Golf Course and Lakeside Pavilion parking lots. The project scope includes parking lot resurfacing, renovation of associated circulation pathways, stormwater management, and landscaping.

Project Updates

June 17, 2022 - Construction continues in the north pavilion parking lot.  Paving will occur the week of June 20th. Landscaping will follow the week of June 27th. Please use caution near the trail between eastern side of the parking lot and lake and on the bike trail along Lexington on the West Side of the parking lot.

June 2, 2022 - Construction has started in the north pavilion parking lot and demolition and grading is currently underway. Please use caution near the trail between eastern side of the parking lot and lake. Finish grading and curbs are anticipated to be installed by the end of next week.  Trail closures will occur for a few days most likely the week of June 13. 

May 20, 2022 - Construction activities continue in the south parking lot. Storms on 5/19 delayed completion of the parking lot and trail paving. Paving scheduled to continue Monday 5/23. Please continue to use detour route until trails reopen. Parking lot will be closed until striping is completed the week of 5/23. The North pavilion lot will be closed immediately following the striping of the south lot for demolition and reconstruction.

May 13, 2022 - Construction activities continue in the south parking lot. Curbs are in and paving should be complete by the end of next week.  Trail closure along the west lakeshore of Como Lake is extended to May 18 due to recent storm events.  The North pavilion lot will be closed immediately following the striping of the south lot for demolition and reconstruction. 

April 29, 2022 - Construction activities continue in the south parking lot including excavation for a new stormwater basin, preparing subbase material for parking lot surfacing, and shoreline work for a non- motorized boat launch. Trail closure along the west lakeshore of Como Lake will occur May 2-13.  Stormwater pipe work will impact 2 parking spaces for 1-2 days each in the north lot and golf course lot. Please see the trail detour map for more information. 

April 22, 2022 - Construction activities continue in the south parking lot including demolition, excavation for a new stormwater basin, and regrading of subbase material will proceed the week of April 25. The north lot and golf course lot are open as usual. Additional parking is available on picnic hill (accessible by the north lot) and at the Butterfly Lot.

April 12, 2022 - Construction will start in the south parking lot beginning the week of April 18 (weather pending). The parking lot will be closed during construction and expected to reopen in early June 2022. Following completion of the south lot, construction on the north parking lot will begin. The north lot is expected to be closed for the month of June while construction is underway. The golf course lot will be closed for construction after Labor Day, on September 6, 2022. It will reopen when construction is complete by early November (pending weather and no unforseen issues).

Como Parking Lot Closures & Alternative Parking Map Como Trail Closure & Trail Detour Map

Community Outreach

The community engagement platform is now closed. 

Saint Paul Parks and Recreation Department is seeking community input on preliminary design. Please click here to provide comments on overall design features and bike/pedestrian trail connections. Thank you for taking your time to comment!

Here is a tutorial to help you navigate the online community engagement map.

 

Meetings

District 10 Land Use Committee Virtual Meeting:  Wednesday, October, 6, 2021 from 7:00-8:00pm

District 10 Land Use Committee Virtual Meeting:  Wednesday, July 1, 2020 from 7:00-8:00pm

 

    Revised Schedule

    Spring 2020:  Analysis
    Summer 2020:  Community Outreach and Engagement & Plan Development
    Late Summer - Fall 2021:  Bid Project for Construction
    Spring 2022: Construction starts