Project Overview
A Community Development Block Grant (CDBG) has been awarded to the City of Saint Paul for improvements at the Conway Park Play Area. The scope of the project will include removal of the existing play equipment and surfacing, new play equipment and surfacing, new site furnishings, and landscaping as funding allows.
Project Updates
Survey #2 is now available!
Please click on the link below to share your thoughts about the play equipment concepts for the new play area at Conway Park!
April 20, 2026
Project staff will be at the Conway Recreation Center on Wednesday, April 22, 2026 for the Earth Day Cleanup event to share initial concepts for the new play equipment at Conway Park! The concepts and a survey to collect feedback will also be posted on the project website after the event.
February 10, 2026
A survey was available between December 2025 and February 2026. Thanks for your feedback! A summary of the comments received can be found below. Project staff will use this feedback to develop concepts for the play equipment and site improvements. Check back soon for more updates and opportunities to share your feedback!
January 8, 2026
Project staff will be at the Conway Recreation Center on Tuesday, January 13th, 2026 at 2pm to share project information and engage with community members during the food distribution event. Staff will also be meeting with kids at the Conway after school program on Thursday, January 15th.
December 2, 2025
Staff virtually attended the Southeast Community Organization's Land-use Committee meeting on December 1, 2025 to share project information about the new Conway Park Play Area. The slides that were shared at this meeting can be found here:
Images of the slides are below:
Preliminary Project Schedule
Date | Phase |
| Nov 2025 – Jan 2026 | Project Start, Schematic Design, and Community Engagement |
| Feb 2026 – Mar 2026 | Design Development and Community Engagement |
| Apr 2026 – Dec 2026 | Community Engagement and Construction Documents |
| Winter 2026/2027 | Bidding |
| Spring 2027 | Construction start (pending bids and weather) |
| Fall 2027 | Target Opening Date |