Project Details
Description
SPRWS is committed to maintaining a reliable and efficient water system for our community. To extend the life of our existing infrastructure and prevent disruptions, we perform ‘cleaning and lining’ projects on aging water mains. These projects involve the cleaning and lining of existing cast iron water mains, a process that effectively refurbishes pipes from the inside, reducing leaks and improving water quality without the need for full replacement.
The scope of this project includes:
- Cleaning and lining of approximately 5,120 feet of cast iron water main to prevent corrosion and enhance water quality.
- Installation or replacement of valves and hydrants to enhance water flow and accessibility for emergency services.
- Repair and restoration of affected street pavement, curbs, and sidewalks to ensure public safety and accessibility.
Location
Dayton and Portland Area
Timeline
2026 Construction Season
- August 28 Update: Dayton pit excavations underway. Portland temporary install in progress.
- August 17 Update: Temporary water installed. Pit excavations underway.
- Limited access traffic patterns in effect.
- August 11 Update: Temporary water installed. Limited access traffic patterns on beginning August 17 with watermain rehab work to follow.
- July 30 Update: Temporary water install scheduled to begin August 10. Water main rehab work to follow.
- Limited access traffic patterns to begin August 17.
- June 11 Update: Preliminary planning and engineering has started.
Contact
Kirill Maloylo